Meeting #11 (7/21/2022)
Began: 4:30pm
Adjourned: 6:18pm
Discussions:
-
Progress log
-
Testing and results
-
Report
Deliverables:
-
Need to add testing pictures to the progress log and report
-
Take the temperature of physical hat
-
Revise Error message test
-
Add error message for product not in database
Meeting #10 (7/18/2022)
Began: 7:02 pm
Adjourned: 5:58 pm
Discussions:
-
Progress on the testing we have completed
-
Project report
Deliverables:
-
Completed project report
Meeting #9 (7/15/2022)
Began: 4:46 pm
Adjourned: 5:31 pm
Discussions:
-
Progress on our project's installation on raspberry pi
-
Project Report
Deliverables:
-
Complete some testing of the project as per the success criteria
Meeting #8 (7/01/2022)
Began: 5:32 pm
Adjourned: 5:58 pm
Discussions:
-
Progress on PaddleOCR installation on the raspberry pi
-
Possible switch to android application or different microcontroller
Deliverables:
-
Project working as intended on raspberry pi
Meeting #7 (6/22/2022)
Began: 4:30 pm
Adjourned: 5:35 pm
Discussions:
-
Progress on Project Report
-
​Discussed revisions to make to chapter 1​
-
Discussed issues installing Paddle OCR on raspberry pi
Deliverables:
-
Revise Chapter 1
-
Start Chapter 2
-
Install Paddle OCR
Meeting #6 (6/16/2022)
Began: 4:31 pm
Adjourned: 5:43 pm
Discussions:
-
Project limitations - wording, possible limitations, error reporting to the user
-
Progress Log
-
Project Report
Deliverables:
-
Project Report
-
Revise last paragraph in abstract to generalize Deep Learning API.
-
Revise Chapter 1
-
Begin Chapter 2
-
-
Raspberry Pi python scripts​
Meeting #5 (6/9/2022)
Began: 4:32 pm
Adjourned: 5:58 pm
Discussions:
-
Website updates from last week's deliverables
-
Progress log
Deliverables:
-
Begin working on text to speech
-
Find a way to separate the products for hand selection
Meeting #4 (6/2/2022)
Began: 4:38 pm
Adjourned:
Discussions:
-
Possible Project limitations
Deliverables:
-
Engineering Requirements - Fix High trial number 2, specify obstructed object.
-
Improve Block diagram to show microcontroller within control module, as well as improve specificity. Discuss Bluetooth button specifications
-
Update Engineering Specifications with discussed improvements
Meeting #3 (5/26/2022)
Began: 4:30 pm
Adjourned: 5:00 pm
Discussions:
-
Updated Engineering requirements
-
Progress Log
Deliverables:
-
Change home page buttons to be the following
-
Engineering requirements​
-
Block Diagram
-
Engineering Specifications
-
-
Progress Timeline to compare with proposal timeline​
-
Add dates to Progress Log
-
Research and implement Data Augmentation to improve object detection model
Meeting #2 (5/19/2022)
Began: 4:30 pm
Adjourned: 5:12 pm
Discussions:
-
Progress Log
-
Engineering Requirements
Deliverables:
-
Increase explanation and detail in progress log
-
Flip time and effort table for latest to be on the top
-
Talk and share our project idea with somebody that is visually impaired to gather their opinion.
Meeting #1 (5/12/2022)
Began: 4:32 pm
Adjourned: 5:21 pm
Discussions:
-
Syllabus, and rubrics for Project, presentation, report and website.
-
Website, project progress, plans for next week
Deliverables:
-
Engineering Requirements
-
Update Progress Log